Seeking Justice
Hold Developers Accountable for Project Tango
By the Numbers
The Impact on Our Community
Plaintiffs Joined
Homes at Risk
From a School
Sq Ft Proposed
Key Issues
Why This Matters
Community Voices
What Our Neighbors Are Saying
We moved to Arden for the nature and tranquility. A 3.69 million square foot data center was never part of that vision. Our families deserve to know what's being built next door.
Maria S.
Arden Resident
My children attend Saddle View Elementary, just 1,500 feet from the proposed site. No parent should have to worry about diesel fumes and industrial noise at their child's school.
James T.
Parent & Homeowner
We were never told about this project when we bought our home. After years of silence, the community finally learned the truth — and we're not going to stay quiet.
Patricia L.
Arden Resident Since 2019
Strength in Numbers

Timeline
How We Got Here
2015
Arden community approved by Palm Beach County (DOA-2015-02352)
2016
BCC rezones adjacent land to Economic Development Center; "data warehouse" approved
2017-24
2,400+ homes sold in Arden with no disclosure of industrial neighbor
2025
Reframed as "data processing center," expanded to 3.69M sq ft
Dec 2025
Commission hearing: 50+ residents speak, 7-0 postponement
Apr 2026
Upcoming County Commission hearing